I-580 Westbound HOV Lane - Greenville to Foothill

Description: In Alameda County on westbound 580. Construct interim HOV lane: Greenville Rd to San Ramon Rd/Foothill Rd.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda
City Dublin, Livermore, Pleasanton
Zip Code 94550, 94551, 94568, 94588
 
Senate District
09, 10
Assembly District 15, 18
Congressional District 10, 11
 
Caltrans District
04
 
 
County/State Route Alameda 580
Postmile Begin/End R  8.3 R  21.4
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  3341    190,759  
Lane Miles Added (HOV)  13.1    7  
Lane Miles Added (Mixed)      0  
Peak Period Time Savings (minutes)  243880    2,613  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Alameda County Transportation Commission Arthur L. Dao (510) 836-2560   adao@actia2022.com
Design (PS&E) Phase
Alameda County Transportation Commission Arthur L. Dao (510) 836-2560   adao@actia2022.com
Right of Way Phase
Alameda County Transportation Commission Arthur L. Dao (510) 836-2560   adao@actia2022.com
Construction Phase
Caltrans Cristina Ferraz (510) 286-3890   cristina_ferraz@dot.ca.gov
 
Corridor System Management Plan
Caltrans Juliana Gum (510) 286-4579   juliana_gum@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$101,700 $-19,359 $82,341
Non-bond Funding
State/Federal*
$0 $33,150 $33,150
Local**
$43,700 $1,186 $44,886
Non Budgeted ETC
$0 $0 $0
 
Total**** $145,400 $14,977 $160,377

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$10,000 $-50 $9,950 $9,950
Design(PS&E)
$2,000 $1,203 $3,203 $3,203
Right of Way
$3,000 $-170 $2,830 $2,832
Construction
$130,400 $13,994 $144,394 $144,856
 
Total* $145,400 $14,977 $160,377 $160,841

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
11/01/2006 

11/01/2009 
 

 
11/01/2006 

01/26/2010 
100  11/01/2006 

01/26/2010 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2008 

03/01/2012 
 

 
11/01/2009 

05/22/2012 
100  11/01/2009 

05/22/2012 


Begin Right of Way Phase

End Right of Way Phase
11/01/2009 

02/01/2012 
 

 
10/01/2009 

03/27/2012 
100  10/01/2009 

03/27/2012 


Begin Construction Phase

End Construction Phase
08/01/2012 

11/01/2014 
03/01/2016 

 
11/20/2012 

11/30/2016 
100  11/20/2012 

09/30/2016 


Begin Closeout Phase

End Closeout Phase
11/01/2014 

11/01/2015 
 

 
12/01/2016 

12/14/2018 
100  01/06/2017 

12/31/2024 
-1 

-74 
Corridor System Management Plan
Adoption Date        
Implementation Date        
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 3341 190,759
Lane Miles Added (HOV) 13.1 7
Lane Miles Added (Mixed) 0
Peak Period Time Savings (minutes) 243880 2,613

Bond Funding Cost
Adopted:
$101,700,000
Current Approved:
$40,481,000
Actual Expenditures:
$40,458,000

 

Status as of December 31, 2023.